Current and Upcoming Capital Projects

Print
Press Enter to show all options, press Tab go to next option

McKelvey Woods Trail Phase II

Great Rivers Greenway has scheduled the grand opening for the trail on June 14th at 5:00 PM at the trail head in Creve Coeur Lake Memorial Park.  

2018 Selective Concrete Pavement Replacement

Work Planned for the Week of June 4 - The contractor will begin delivery of traffic control devices and sawcutting of slabs in the 2400 and 2500 blocks of Pheasant Run Drive. Utility locates will also take place in this area. Actual construction is scheduled for the week of June 11. 

Upcoming Capital Projects

2018 Asphalt Program -  This project will be the milling and overlay of Smiley Road from Midland Avenue to Terry Avenue. The preconstruction meeting for this project is scheduled for June 6th. The construction schedule will be discussed in this meeting. 

Delord Avenue Reconstruction -  The preconstruction meeting for this project has not been scheduled at this time.  

Grissom Drive Reconstruction -  Property appraisals have been completed. Easement and right of way acquisition will be starting by July 1.  

Sylvan Manor Sidewalk Project -  Easement acquisition is underway.  

Upcoming Information/Questions

It is the City's goal to provide updates as the project progresses.  If you have any questions on the project, feel free to contact any of the City's employees listed in this e-mail. 