Road Projects Update

Print
Press Enter to show all options, press Tab go to next option

 

City of Maryland Heights

Department of Public Works

 

CAPITAL PROJECTS IN THE WORKS

April 21, 2017

 

 

 

McKelvey Woods Nature Park Trail

 

 

Work Completed - The prefabricated pedestrian bridge was set. Placement of backfill at the bridge took place.

 

Work Planned for the Week of April 24- Pouring of the prefabricated pedestrian bridge deck is scheduled. Finish grading of the trail to match the bridge is planned.

 

 

McKelvey Woods TrailPhase II

 

 

Work Completed - Grading of the trail in Creve Coeur Park took place. Placement of the gravel base on this section of trail began.

 

Work Planned for the Week of April 24- Construction of thetrail through Creve Coeur Park is scheduled to continue. Placement of fill material for the trail in the wetlands area will continue.

 

 

Adie Road Phase III

 

 

Work Completed - Excavation for thebiobasin along Chaffee Drive took place.

 

Work Planned for the Week of April 24-Work on the bio basin along Chaffee Drive is planned. Completion of the sidewalk near Chaffee Drive is scheduled.

 

 

11825 Hollycrest Ct., 2436 Charente Dr., Covernty Trail Stormwater Projects

 

 

Work Completed - Finish grading in the rear yards and placement of sod on Hollycrest Court took place. Construction of the storm sewer system at Coventry Trail began.

 

Work Planned for the Week of April 24- Construction of the Coventry Trail storm sewer project will continue.

 

 

2017 Asphalt Paving

 

 

Work Planned for the Week of April 24- Construction of the widening along Monima Road will begin. Milling and overlay on Dunlap Industrial Drive is scheduled.

 

 

Upcoming Information/Questions

 

It is the City's goal to provide updates as the project progresses.If you have any questions on the project, feel free to contact any of the City's employees listed in this e-mail.

 

Cliff Baber, P.E.

Construction Manager

314-738-2258

cbaber@marylandheights.com

 

Bryan Pearl, P.E.

Director of Public Works

314-738-2251

bpearl@marylandheights.com

 

12131 Diane Marie Drive Storm Water Project

 

Work Completed- Options to continue construction were discussed with the design engineer and Missouri American Water Company.

Planned for the week of March 14- No work planned.

12131 Diane Marie Drive Storm Water Project

 

Work Completed- Options to continue construction were discussed with the design engineer and Missouri American Water Company.

Planned for the week of March 14- No work planned.