Road Projects Update

Print

 

City of Maryland Heights

Department of Public Works

 CAPITAL PROJECTS IN THE WORKS

September 2, 2016

 

 

 

 

 

Progress Parkway

 

Work Completed - Paving of the majority of the northbound lane from Progress Service Drive to Kimler Drive took place.      

Planned for the Week of  September 5 Paving of the last section of the northbound lane from Progress Service Drive to Kimler Drive is scheduled. Paving of the inlet sumps and driveway approaches along the new pavement will begin.

Progress Parkway remains one-way northbound from Progress Service Drive to Kimler Drive.

 

 

 

 

Adie Road Phase III

 

Work Completed- Paving of the remainder of the center lane from Fee Fee Road to Centerline Industrial Drive took place. Removal of the old bridge and excavation for the new structure began.  

Planned for the week of September 5-  Paving of the eastbound lane from Centerline Industrial Drive to the railroad tracks is planned. Forming and pouring of the footings for the new bridge is planned to begin.

NOTE: Adie Road is closed to all traffic at the creek. 

Adie Road continues to be one-way eastbound from Fee Fee Road to Centerline Industrial Drive. In addition Chaffee Drive is closed at Adie Road.

 

 

Brookside Sidewalk Phase II

 

 

 

 

This project is on hold until after September when the sod can be installed.

 

 

 

 

Upcoming Information/Questions

 

It is the City's goal to provide updates as the project progresses.If you have any questions on the project, feel free to contact any of the City's employees listed in this e-mail.

 

Cliff Baber, P.E.
Construction Manager
314-738-2258
cbaber@marylandheights.com

 

Bryan Pearl, P.E.
Director of Public Works
314-738-2251
bpearl@marylandheights.com

 


12131 Diane Marie Drive Storm Water Project

 

Work Completed- Options to continue construction were discussed with the design engineer and Missouri American Water Company.

Planned for the week of March 14- No work planned.

12131 Diane Marie Drive Storm Water Project

 

Work Completed- Options to continue construction were discussed with the design engineer and Missouri American Water Company.

Planned for the week of March 14- No work planned.