Capital Project Update - Week of Jan. 28
Posted Date: 1/28/2013

Heights Area Storm Sewer

Work Completed: No work was completed. We are waiting on MSD and railroad approval of the revisions to the pipe location under the railroad.

McKelvey Woods Court

Work Completed: No work was performed. This project is on hold until the trail project is completed.

McKelvey Woods Trail

Work Completed: Forming of bridge foundations took place.

Work Planned for the week of Jan. 28: Pouring of bridge foundations is planned.

Upcoming Information/Questions

It is the city's goal to provide updates as each project progresses. If you have questions on any project, feel free to contact us.