Capital Improvements Projects Update

The following is a brief update of the current Capital Projects as of March 1, 2024:

2024 Concrete Replacement Program
Construction is expected to begin April 1. Pavement replacement will take place in Parkland Woods and Autumn Lakes subdivisions.

Adie Road (Dorsett Rd. to Lindbergh Blvd.)
Construction is expected to begin April 1. The road is scheduled to be closed to through traffic from April 1 - mid-August. After August, the road will be open to one-way traffic going northbound. This project is scheduled to be completed by the end of October.

Get the latest updates at www.marylandheights.com/PublicWorks and click on "Project Updates." If you have any questions on the projects listed, contact staff at (314) 738-2250.